R-64-08 Resolution Approving Change Order for PD Water Detention BasinRESOLUTION - lU `C
RESOLUTION AUTHORIZING APPROVAL OF A CHANGE ORDER #8
TO THE GMAX POLICE BUILDING CONTRACT WITH WIGHT FOR
SHARED STORM WATER DETENTION BASIN
WHEREAS, the Village of Lemont approved a design/build contract with Wight Construction for the
construction of its new Police Facility; and
WHEREAS, the contract with Wight Construction included a Guaranteed Maximum Price for the
scope of the contract; and
WHEREAS, the Village of Lemont requires the construction of a storm water detention basin in
conjunction with the Lemont Police Facility construction contract;
WHEREAS, on July 14, 2008 the Village Board passed a resolution approving a temporary
construction and permanent storm water and drainage easement from St. Matthew Evangelical Lutheran
Church to construct said detention basin; and
WHEREAS, the shared storm water detention basin was not included in the scope of the Guaranteed
Maximum Price Contract but will be added as a change order to said contract;
NOW, THEREFORE, BE IT RESOLVED by the President and Board of Trustees that a Change
Order to the Guaranteed Maximum Price Contract with Wight Construction shall be authorized for an amount
not to exceed $314,910.00.
PASSED AND APPROVED BY THE PRESIDENT AND BOARD OF TRUSTEES OF
THE VILLAGE OF LEMONT, COOK, WILL AND DU PAGE COUNTIES ILLINOIS on this
�7 Day of )J-.0/ , 2008
Debby Blatzer
Peter Coules
Brian Reaves
Cliff Miklos
Ronald Stapleton
Jeanette Virgilio
Attest:
AYES NAYS PASSED ABSENT
JOHN F. PIAZZA, Vi t age Ptesl t
i
CHARLENE SMOLLEN, Village Clerk
SUBCONTRACTOR CHANGE ORDER
VILLAGE OF LEMONT POLICE FACILITY
Village of Lemont
418 Main Street
Lemont, IL 60439
Design Builder's Project No.: 07- 5011 -03
TO. Wight Construction, Inc.
2500 N. Frontage Road
Darien, IL 60561
630 - 969 -7000
You are hereby directed to make the following changes in the Contract:
Item Description
01 Shared Stormwater Detention Basin
Bid Package #26 Base Bid Scope $137,500.00 Hoppy's Landscaping
Haul -Off Unit Price Allowance 122,500.00 Floppy's Landscaping
Subtotal Hard Cost 260,000.00
CM Fee 3.5% $ 9,100.00
NE Fee 7.6% $19,760.00
General Conditions LS $18,250.00
Contingency 3.0% 7,800.00
DATE: 9/17/2008
VILLAGE OF LEMONT
418 Main Street
Lemont, IL 60439
Design Build/ Construction Management,
/'1
Prepared By:
Approved By:
CHANGE ORDER NUMBER: VOL -09
CONTRACT FOR: 004 -002 - Design Build Services
CONTRACT DATE: 3/3/2008
Quantity Unit Price
Net Amount
1.000 $314,910.00 $314,910.00
Total: $314,910.00
Not valid until signed by the Design Builder
Signature of the Contractor indicates his agreement herewith, including any adjustment in the Contract Sum or contract time.
The original Contract Sum was:
Net change by previously authorized requests and changes:
The Contract Sum prior to this Change Order was:
The Contract Sum will be Increased by this Change Order:
The new Contract Sum including this Change Order will be:
The Contract Time will not be changed.
The Date of Substantial Completion as of this Change Order therefore is
$7,724,293.00
$219,056.45
$7,943,349.45
$314,910.00
$8,258,259.45
Authorized:
DESIGN BUILDER:
Village of Lemont
418 Main Street
Lemont, IL 60439
By:
Date:
f_co_01_wight
; A,
02 Of
CONTRACTOR:
Wight Construction, Inc.
2500 N. Frontage Road
Darien, IL 60561
By:
Date: