R-87-00 10/09/00RESOLUTION k /' Off` RESOLUTION AUTHORIZING CONTRACT CHANGE ORDER FOR CONSTRUCTION SERVICES RENDERED IN CONJUNCTION WITH THE LOGAN STREET DAM RECONSTRUCTION PROJECT WHEREAS, the Village of Lemont has previously awarded a construction contract to Earth Werks, Inc. for the Logan Street dam Reconstruction Project, and WHEREAS, the Village of Lemont has determined that certain changes to the contract totaling $ 18,739.00 are necessary to satisfactorily complete the construction project; and WHEREAS, the contract changes are a result of final quantities as measured in place or changes that were not originally contemplated at the time the contract was awarded. NOW, THEREFORE, BE IT RESOLVED, by the President and Board of Trustees that the Contract Change Order with Earth Werks, Inc. in the amount of $ 18,739.00 is hereby approved. PASSED AND APPROVED BY THE PRESIDENT AND BOARD OF TRUSTEES OF THE VILLAGE OF LEMONT, COUNTIES OF COOK, WILL AND DUPAGE, ILLINOIS, on this 9th day of October , 2000. John Benik Debby Blatzer Keith Latz Connie Markiewicz Rick Rimbo Mary Studebaker AYES NAYS PASSED ABSENT v v V C ARLENE SMOLLEN, Village Clerk Approved by me this 9th day of Attest: 1 ?Mk AIL AIL •I ARD I =WAS October , 2000. CHARLENE SMOL Approved to form. 1 HN A ` ONOPOULOS, i r ge Attorney sident Village of Lemont Project: Logan Street Spillway Owner: Village of Lemont 418 Main Street Lemont, Illinois 60439 Contractor: Earth Werks, Inc. 170 -A Alexandra Way Carol Stream, IL 60188 Authorization of Contract Changes Authorization Summary Date: 10 -27 -1999 through 05 -10 -2000 Engineer: Christopher B. Burke Engineering, Ltd. 9575 West Higgins Road, Suite 600 Rosemont, Illinois 60018 -4920 The following change from the plans in the construction of the above designated project is authorized and directed. The estimated quantities are shown below at the awarded contract prices except as indicated. The first addition of an item not in the original contract is indicated by an asterisk ( "). AUTHORIZATION NO. 1 ITEM NO. * PAY ITEM UNIT QUANTITY UNIT PRICE A/D ADDITION DEDUCTION N/A * Removal of Concrete Debris Lsum 1.00 $ 6,000.00 A $ 6,000.00 Totals: Net Change: $ 6,000.00 $ - $ 6,000.00 DESCRIPTION: Concrete debris was dumped and placed on the project site, at the request of the Public Works Department, for protection of the spillway prior to construction. This material was placed on the site after the project was bid. AUTHORIZATION NO. 2 ITEM NO. * PAY ITEM UNIT QUANTITY UNIT PRICE A/D ADDITION DEDUCTION 54202959 N/A Pipe Culverts, Type 4 RCCP 24" * Pipe CuIv, 18" C900 w/ Conc Cr & Underdrn Foot Foot - 112.00 112.00 $ 45.00 $ 103.00 D A $ 11,536.00 $ 5,040.00 Totals: $ 11,536.00 $ 5,040.00 Net Change: $ 6,496.00 DESCRIPTION: The size and type of pipe were changed as a result of safety permit modifications by the Illinois Department of Natural Resources. AUTHORIZATION NO. 3 ITEM NO. * PAY ITEM UNIT QUANTITY UNIT PRICE A/D ADDITION DEDUCTION -20500150 20700420 21101300 25001100 25100630 28000400 28000500 28100105 50300220 50800205 N/A N/A N/A N/A N/A Embankment Porous Granular Embankment, Subgrade Furnishing and Placing Topsoil, 4" Seeding, Class 3 (Special) Erosion Control Blanket Perimeter Erosion Barrier Inlet and Pipe Protection Stone RipRap, Class A3 Concrete Structures Reinforcement Bars, Epoxy Coated Removal of Unsuitable Materials Articulated Concrete Mats, Class 50T Topsoil for Articulated Concrete Mats * Replace Manhole Frames & Lids, Watertight * Replace Manhole Frames & Lids, Watertight CY CY SY AC SY LF EA SY CY LB CY SY SY EA EA 283.00 - 331.00 -34.00 0.05 -78.00 6.00 -2.00 13.00 -15.00 3144.00 538.00 85.00 85.00 1.00 4.00 $ 7.00 $ 25.00 $ 2.50 $ 5,000.00 $ 1.25 $ 2.00 $ 300.00 $ 45.00 $ 600.00 $ 1.00 $ 22.00 $ 18.00 $ 2.50 $ 750.00 $ 1,000.00 A D D A D A D A D A A A A A A $ 1,981.00 $ 250.00 $ 12.00 $ 585.00 $ 3,144.00 $ 11,836.00 $ 1,530.00 $ 212.50 $ 750.00 $ 4,000.00 $ 8,275.00 $ 85.00 $ 97.50 $ 600.00 $ 9,000.00 Totals: Net Change: $ 24,300.50 $ 18,057.50 $ 6,243.00 DESCRIPTION: These changes represent the field measured changes for each individual item. The items for Replace Manhole Frames & Lids, Watertight, were added so that four upstream manholes would be brought into compliance with current MWRD regulations. Page 1 of 2 Village of Lemont Project: Logan Street Spillway Owner: Village of Lemont 418 Main Street Lemont, Illinois 60439 Contractor: Earth Werks, Inc. 170 -A Alexandra Way Carol Stream, IL 60188 Authorization of Contract Changes Authorization Summary Date: 10 -27 -1999 through 05-10 -2000 Engineer: Christopher B. Burke Engineering, Ltd. 9575 West Higgins Road, Suite 600 Rosemont, Illinois 60018 -4920 The following change from the plans in the construction of the above designated project is authorized and directed. The estimated quantities are shown below at the awarded contract prices except as indicated. The first addition of an item not in the original contract is indicated by an asterisk ( *). CHANGES TO THE CONTRACT PRICE Original CONTRACT PRICE: The CONTRACT PRICE due to these CHANGE ORDERS will be INCREASED by: The new CONTRACT PRICE including these CHANGE ORDERS will be: $ 357,742.50 $ 18,739.00 $ 376,481.50 CHANGES TO CONTRACT TIME The CONTRACT TIME was not affected by these agreements. AUTHORIZED SIGNATURES Approved by OWNER . Date Page 2 of 2