R-41-01 Authorizing contract change order for construction services and materials in conjunction with state street well (no.3) rehabilitationRESOLUTION ie--H-0/ RESOLUTION AUTHORIZING CONTRACT CHANGE ORDER FOR CONSTRUCTION SERVICES AND MATERIALS IN CONJUNCTION WITH STATE STREET WELL (NO. 3) REHABILITATION WHEREAS, the Village of Lemont has previously awarded a construction contract to Layne - Western for rehabilitation of Well #3; and WHEREAS, the Village of Lemont has determined that certain changes to the contract totaling $27,423.50 are necessary to satisfactorily complete the construction project; and WHEREAS, the contract changes reflect materials and services which could not be identified at the time the contract was awarded. NOW THEREFORE BE IT RESOLVED by the President and Board of Trustees that the contract change order with Layne- Western in the amount of $27,423.50 is hereby approved. PASSED AND APPROVED BY THE PRESIDENT AND BOARD OF TRUSTEES OF THE VILLAGE OF LEMONT, COUNTIES OF COOK, WILL, AND DU PAGE, ILLINOIS on this 9th day of July . 2001. John Benik Debby Blatzer Peter Coules Connie Markiewicz Steven Rosendahl Jeanette Virgilio AYES NAYS PASSED ABSENT CHARLENE SMOLLEN, Village Clerk Approved by me this 9th day of July , 2001. AZZA, Village Pre Attest: CHARLENE SMOLLEN, Village Cler Approved as to form: Village Attorney Date: Iinois ❑ 60521 ❑ 630 - 887 -8640 ❑ fax: 630 - 887 -0132 WIMP / -" FRANK NOVOTNY 8 ASSOCIATES, INC. CONSUL T /NG C /V /L ENG /NEERS Mr. Gary Holmes Administrator Village of Lemont 418 Main Street Lemont, Illinois 60439 Re: State Street Well (No. 3) Rehabilitation Change Order No. 1 Dear Gary: June 29, 2001 • As you know, the final project cost for the above - captioned project is $166,343.50, which is $27,423.50 (19.7 %) over the awarded Contract price of $138,920.00. The reason for this overage is as follows: • Bailing of sand fill • Installation of 10" Steel Line Pipe and 10" liner shoe, and • 2" PVC Flush -Joint pipe for water level transducer Bailing Sand Fill This is a normal maintenance item, but it can't be done until the pump is pulled out of the well hole. Over a period of time, sand washes in from the sides of the well hole. The last time the well was bailed was 1984, and we included a unit price proposal per hour for bailing sand. The Contractor bailed sand for 38 oo hours, at which time he was directed to stop. This cost was $5,936.00. •a Installation of 10" Steel Line Pipe and 10" Liner Shoe •3 Once the well pump was pulled out of the hole, the liner pipe was televised. It was noted to the existing 83 feet of steel line pope was totally deteriorated on one side. The liner pipe protects the well hole from shale caving in and blocking > the areas of water yield. It was decided to completed replace the 10" and 12" v liner pipe at this time. The cost of this work was $18,442.50. This work can be considered normal maintenance, but it can only be performed when the well 3 equipment is pulled out of the hole. N 00 Mr. Gary Holmes Village of Lemont June 29, 2001 Page Two 2" PVC Flush -Joint Pipe for Water Level Transducer This item was installed in order to electronically measure the water level in the well, at the request of the Water Department. The cost of this work was $3,045.00. The total of this work is $27,423.50, the net overage. I hope this explains the cause of this work. Please cal if you have any questions concerning this matter. Very truly yours, FRANK O ► Y & ASSOCIATES, INC. a %'es . Cainkar, P.E., P.L.S. JLC /debi cc: Mr. Dan Fielding, Dir. of PW Project File No. 00278 FRANK NOVOTNY 8 ASSOCIATES, INC CONSUL T /NG C /V /L ENG /NEERS q June 27, 2001 O Mr. Gary Holmes ■ I� Administrator OD Village of Lemont co 418 Main Street Lemont, Illinois 60439 co CO p Dear Gary: 00 This letter is to certify that Layne - Western has satisfactorily furnished labor and material in accordance with the terms of their Contract, and as outlined on the attached 03 000 "Engineer's Payment Estimate No. 2 & Final ". O The Contractor has completed all work in a satisfactory manner. The final contract CO cost of $166,343,50 is $27,423.50 (19.7 %) over the awarded contract value of ❑ $138,920.00. The extra work included sand bailing, installation of a transducer, and replacement of the entire liner pipe. This work was performed in accordance with Village N directives. O �O A Change Order in the amount of $27,423.50 is included for approval by the ❑ Village, in accordance with applicable State Statute. .cn We therefore recommend the payment of $83,322.33 to be paid to LAYNE- WESTERN, 721 West Illinois Avenue, Aurora, IL 60506. Attached please find Contractor's Matching Invoice, with "Final Waiver of Lien" and "Contractor's Affidavit" in the - aforementioned amount. 0 0 Please call if you have any questions concerning this matter. Re: State Street Well (No. 3) Rehabilitation Engineer's Payment Estimate No. 2 & Final 0 a) co JLC /dam Enclosure co Very truly yours, FRA ASSOCIATES, INC. Cainkar, P.E., P.L.S. cc: Mr. Dan Fielding, Dir. of PW, w /Enc. Layne - Western (c/o Mr. Thomas Healy), w /Enc. Project File No. 00278 PAYMENT ESTIMATE OWNER: Village of Lemont PROJECT DESCRIPTION: State Street Well (No. 3) Rehabilitation PAYMENT TO: ESTIMATE NO.: Layne - Westem, 721 W. Illinois Avenue, Aurora, IL 60506 2 & Final FROM: April 30, 2001 Page 1 Of 1 PROJECT NO : 00278 TO: June 22, 2001 Item No Description Awarded Approved For Payment Unit Quantity Amount Over Under Quantity Unit Price Amount BASE BID 1 Mobilization and demobilization of pump service equipment L.S. 1 $2,775.00 1 $2,775.00 $ 2,775.00 2 Remove and dispose of lineshaft pump, including inspection; measuring depths; bailing oil; etc. L.S. 1 10,950.00 1 10,950.00 10,950.00 3 Television Survey of Well L.S. 1 1,375.00 1 1,375.00 1,375.00 4 Fumish new Byron Jackson submersible pump with cast iron bronze fitted (CIBF) bowl assembly L.S. 1 104,855.00 1 104,855.00 104,855.00 5 Install and test new submersible pump, complete L.S. 1 9,975.00 1 9,975.00 9,975.00 SUPPLEMENTAL PRICING 1 Bailing sand fill HOUR 28 28 212.00 5,936.00 2 Addition for synergistic nickel oxide coating of cast iron bowl surfaces L.S. 1 8,990.00 1 8,990.00 8,990.00 SUBMITTAL INFORMATION 1 Please list Contractor performing television survey of well, who will also certify that the TV equipment has only been used in water wells. Name of Contractor: Layne - Westem 2 Pump service rig to be used: Name: Speedstar PU Heavy or W550 -HD "Approved Additional Work" Serviceman (Liner Prep - Fabricate Centralizers and Cal Seal Bullet, and Loading) HOUR 8.5 8.5 83.00 705.50 Equipment and 4 Men (5 -11 -01 and 5 -12 -01) HOUR 16 16 365.00 5,840.00 Equipment and 3 Men Overtime (5 -11 -01) HOUR 3 3 406.50 1,219.50 Equipment and 4 Men Overtime (5 -12 -01) HOUR 4 4 514.50 2,058.00 Serviceman Overtime (5 -12 -01) HOUR 4 4 124.50 498.00 Equipment and 2 Men (5 -14-01) HOUR 7 7 212.00 1,484.00 Television Surveys (No charge on 2 Others) L.S. 2 2 1,375.00 2,750.00 Additional Helper for Installation of 2" Flush -Joint HOUR 22.5 22.5 72.00 1,620.00 PVC and Transducer 2" PVC Flush -Joint Pipe for Transducer L.S. 1 1 1,425.00 1,425.00 10" Schedule 40 Prime Steel Liner Pipe FEET 83 83 37.50 3,112.50 10" Liner Shoe L.S. 1 1 775.00 775.00 TOTAL: $ 138,920.00 $ 166,343.50 RECOMMENDED F FRANK NO T BY: INC. BY: James L. Cainkar, P.E., P.L.S. DATE: June 25, 2001 Total Value of Completed Work $ 166,343.50 Less 0% Retained Sub -Total $ 166,343.50 Less Payment Estimate No. 1 $ 83,021.17 TOTAL THIS PAYMENT ESTIMATE NO. 2 $ 83,322.33 & FINAL Request for Approval of Change in Plans Date: June 27, 2001 County Cook, DuPage & Will Contractor: Layne - Westem Road District or Municipality Lemont 721 West illinois Avenue Aurora, Illinois 60506 Section N/A I recommend that ar addition be made to the above contract. Request No. 1 & Final Between Station N/A and Station N/A (Do not fill in unless a change in length is involved.) The estimated quantities are shown below and the Contract agrees to furnish the materials and do the work at the Contract unit prices. Shown station location for major items. Item Awarded No Description Unit Quantity Amount Over Under Quantity Unit Price Additions Deductions BASE BID 1 Mobilization and demobilization of pump service LS. 1 S 2,775.00 1 2,775.00 equipment $ - 2 Remove and dispose of iineshaft pump, including L.S. 1 $ 10,950.00 1 10,950.00 inspection; measuring depths; bailing oil: etc. $ - 3 Television Survey of Well L.S. 1 $ 1,375.00 1 1,375.00 4 Furnish new Byron Jackson submersible pump with cast iron bronze fitted (CIBF) bowl assembly L.S. 1 S 104,855.00 1 104.855.00 5 Install and test new submersible pump, complete L.S. 1 3 9,975.00 1 9,975.00 SUPPLEMENTAL PRICING 1 2 Bailing sand fill Addition HOUR 28 28 212.00 55,936.00 for synergistic nickel oxide coating of cast iron bowl surfaces L.S. 1 $ 8,990.00 1 8,990.00 "Anoroved Additional Work" Serviceman (Liner Prep - Fabricate Centralizers and Cal Seal Bullet, and Loading) HOUR 8.5 8.5 83.00 3705.50 Equipment and 4 Men (5-11-01 and 5 -12 -01) Equipment and 3 Men Overtime (5 -11 -01) Equipment HOUR HOUR • 16 3 16 3 365.00 406.50 55,840.00 51 21850 and 4 Men Overtime (5 -12 -01) Serviceman HOUR 4 4 514.50 52,058.00 Overtime (5 -12 -01) Equipment HOUR 4 4 124.50 $498.00 and 2 Men (5 -14 -01) Television HOUR 7 7 212.00 31,484.00 Surveys (No charge on 2 Others) Additional LS. 2 2 1,375.00 32,750.00 Helper for Installation of 2' Flush -Joint PVC and Transducer HOUR 22.5 22.5 72.00 31,620.00 2' PVC Flush -Joint Pipe for Transducer L.S. 1 1 1,425.00 51,425.00 10' Schedule 40 Prime Steel Liner Pipe 10' FEET 83 83 37.50 53 11250 Liner Shoe L.S. 1 1 775.00 3775.00 5138,920.00 Totals: $ 27,423.50 5 - Total net addition to date $ 27,423.50 which is 19.74% of Contract price. Net Change: $ 27,423.50 5 - Page 1 of 2 State fully the nature and reason for the change: Adjustment for as- constructed quantities in comparison to Plan quantities. When the net increase or decrease in the cost of the contract is $10,000 or more or the time of completion is increased or decreased by 30 days or more, one of the following statements shall be checked. XX The undersigned determine that the circumstances which necessitate this change were not reasonably foreseeable at the time the contract was signed. The undersigned determine that the circumstances which necessitate this change were not within the contemplation of the contract as signed. The undersigned determine that this change is in the best interest of the local agency and is authorized by law. Signed: Signed: Date Approved Recommended Municipal Offier Mr. Gary Holmes, Administrator Title of Municpal Offier 27 -Jun -01 Date Approved County Engineer District Engineer Date Date Note: Make out separate form for change in length quantities. Give net quantities only. Submit 3 copies of this form to District Engineer (4 copies for road district) If plans are required attach 3 sets. Page 2 of 2 (11977.) LAYNE- WESTERN a division of Layne Christensen Company 721 W. Illinois Avenue • Aurora, IL 60506 -2892 Telephone 630/897 -6941 • FAX 630/897 -6976 TO Frank Novotny and Associates 825 Midway Drive Willowbrook, IL 60521 WE ARE SENDING YOU nShop Drawings Copy of letter LETTER OF TRANSMITTAL Date June 19, 2001 Job No. Attention Jim Cainkar RE: Lemont, IL Well No. 3j .4 .I 2001 Attached 0 Under separate cover via n Prints n Plans n Samples = Change Order the following items: n Specifications 0 COPIES DATE NO. DESCRIPTION 2 6 -19 -01 Invoice No. 10162896 — Pay Request No. 2 — Final 2 6 -19 -01 Waiver of Lien /Contractor's Affidavit 5 6 -1 -01 Well Test Data Sheet 1 Set Daily Reports — Documentation for Extra Work 1 6 -5 -01 Novotny Field Test Report 1 Evaluation Card THESE ARE TRANSMITTED AS CHECKED BELOW: For approval For your use EDAs requested For review and comment ElApproved as submitted ElApproved as noted Returned for corrections Resubmit copies for approval LDSubmit copies for distribution Retum corrected prints = FOR BIDS DUE 19 = PRINTS RETURNED AFTER LOAN TO US REMARKS Jim: Please find enclosed the above documents, which should complete the Well No. 3 project. The test results and observations indicate that the new pump is operating quite satisfactorily. There were certainly some very trying times along the way, but the Village should be very happy with the end result! It has been a pleasure working with you on the project. COPY TO: SIGNED: Thomas P. Healy, P.E., Assistant Di ict Manager 061901.DOC FINAL WAIVER OF LIEN STATE OF ILLINOIS COUNTY OF KANE TO WHOM IT MAY CONCERN: Gry# Loan# WHEREAS the undersigned has been employed by Village of Lemont to fumish Labor, equipment and materials for the premises known as State Street Well No. 3 of which Village of Lemont, IL is the owner. The undersigned, for and in consideration of Eighty Three Thousand Three Hundred Twenty Two dollars and 33/100 ($ 83,322.33 ) Dollars, and other good and valuable considerations, the receipt whereof is hereby acknowledged, do(es) hereby waive and release any and all lien or claim of, or right to, lien, under the statutes of the State of Illinois, relating to mechanics' liens, with respect to and on said above - described premises, and the improvements thereon, and on the material, fixtures, apparatus or machinery furnished, and on the moneys, funds or other considerations due or to become due from the owner, on account of labor services, material, fixtures, apparatus or machinery, furnished to this date by the undersigned for the above —described premises. Given Under our Hand s and Seal ed This of June 20 01 1 9th Signature and Seal: day LAYNE- WESTERN a division of Layne Christensen Company Thomas P. Healy, P.E., Assistant District Ma . . • er NOTE: All waivers must be for the full amount paid. If waiver is for a corporation, corporate name should be used, corporate seal affixed and title of officer signing waiver should be set forth; if waiver is for a partnership, the partnership name should be used, partner should sign and designate himself as partner. STATE OF ILLINOIS COUNTY OF KANE TO WHOM IT MAY CONCERN: THE undersigned, being duly sworn, deposes and says that he is Assistant District Manager J CONTRACTOR'S AFFIDAVIT of the Layne - Westem, a division of Layne Christensen Company who is the contractor for the Village of Lemont building located at 1179 State Street (Well No. 3) owned by Village of Lemont, Illinois That the amount of the contract including extras is $ 166,343.50 on which he has received $ 83;021.17 prior to this payment. That all waivers are true, correct and genuine and delivered unconditionally and that there is no claim either legal or equitable to defeat the validity of said waivers. That the following are the names of all parties who have furnished material or labor, or both, for said work and all parties having contracts or subcontracts for specific portions of said work or for material entering into the construction thereof and the amount due or to become due to each, and that the items mentioned include all labor and material required to complete said work according to plans and specifications. work on the NAMES WHAT FOR CONTRACT PRICE AMOUNT PAID THIS PAYMENT BALANCE DUE Layne - Western, a division of Labor and materials 138,920.00 83,021.17 55,898.83 0.00 Layne Christensen Company Extra Work 27,423.50 0.00 27,423.50 0.00 TOTAL LABOR AND MATERIAL TO COMPLETE 166,343.50 83,021.70 83,322.33 0.00 That there are no other contracts for said work outstanding, and that here is nothing due or to become due to any person for material, labor or other work of any kind done or to be done upon or in connection with said work other than above stated. Signed this 19'h day of June , 2001 LAYNE- WESTERN, a division of Layne Ch " tensen ompany Subscribed and sworn 061901 Signature ore me this OFFICIAL SEAL KRISTI A. RODRIGUEZ NOTARY PUBLIC, STATE OF ILLINOIS MY LION EXPIRES 545-2005 Thom ?s P. Healy, P.E., Assistant District M. nager day of },[� a. 0 Kristi A. Rodriguez, N ,2001. 0. Layne Christensen Company LAYNE- WESTERN DIVISION Remit to: P.O. Box 91090 Chicago, IL 60693 721 West Illinois Avenue - Aurora, Illinois - 60506 -2892 Phone (630) 897 -6941 Fax (630) 897 -6976 229 West Indiana Avenue - Beecher, Illinois - 60401 -0489 Phone (708) 946 -2244 Fax (708) 946 -9415 INVOICE 10162896 SOLD TO: VILLAGE OF LEMONT 418 MAIN STREET LEMONT, IL 60439 TERMS: Due on receipt Page: 1 of 3 DATE: 06/18/2001 PO # CONTRACT OUR ORDER NO.: 168650 CLIENT NO.: 10160047 QUANTITY DESCRIPTION AMOUNT TOTAL FOR THE COMPLETION OF THE STATE ST. WELL (NO. 3) REHABILITATION - BASE BID ITEMS - 1 L.S. 1. MOBILIZATION AND DEMOBILIZATION 1 L.S. 2. REMOVE AND DISPOSE OF LINESHAFT PUMP 1 L.S. 3. TELEVISION SURVEY 1 L.S. 4. FURNISH NEW BYRON JACKSON SUBMERSIBLE PUMP 1 L.S. 5. INSTALL NEW BYRON JACKSON SUBMERSIBLE PUMP - SUPPLENENTAL ITEMS - 28 HRS. SAND BAILING AND RELATED WORK 1 L.S. NICKEL OXIDE COATING ON BOWL 2,775.00 10,950.00 1,375.00 104,855.00 9,975.00 Subtotal BASE BID ITEMS 212.00 8,990.00 Subtotal SUPPLENENTAL ITEMS EXTRA WORK, RELATED TO INSTALLATION OF NEW 10" LINER 5- 10,11, AND 12 -2001 2,775.00 10,950.00 1,375.00 104,855.00 9,975.00 129,930.00 5,936.00 8,990.00 14,926.00 Layne Christensen Company will institute a late payment charge at a rate of 18% per annum (unless a lower rate is required under applicable law, in which case the lower rate shall apply) for all payments not made on or before the due date. It is the policy of Layne Christensen to preserve all lien and payment bond rights where available. All notifications are sent strictly for this purpose. - 000RI- Thank you for your business Remittance Copy Layne Christensen is an Equal Opportunity Employer (Continued) Layne Christensen Company LAYNE - WESTERN DIVISION Remit to: P.O. Box 91090 Chicago, IL 60693 721 West Illinois Avenue - Aurora, Illinois - 60506 -2892 Phone (630) 897 -6941 Fax (630) 897 -6976 229 West Indiana Avenue - Beecher, Illinois - 60401 -0489 Phone (708) 946 -2244 Fax (708) 946 -9415 INVOICE 10162896 SOLD TO: VILLAGE OF LEMONT 418 MAIN STREET LEMONT, IL 60439 TERMS: Due on receipt Page: 2 of 3 DATE: 06/18/2001 PO # CONTRACT OUR ORDER NO.: 168650 CLIENT NO.: 10160047 QUANTITY DESCRIPTION AMOUNT TOTAL 8.50 HRS. 5- 10,11, AND 12 -2001 SERVICEMAN (LINER PREP - FABRICATE CENTRALIZERS AND CAL SEAL BULLET, AND LOADING) 83.00 5 -11 -01 8 HRS. EQUIPMENT AND 4 MEN 365.00 3 HRS. EQUIPMENT AND 3 MEN OVERTIME 406.50 8 HRS. 4 HRS. 4 HRS. 5 -12 -01 EQUIPMENT AND 4 MEN EQUIPMENT AND 4 MEN OVERTIME SERVICEMAN OVERTIME 365.00 514.50 124.50 5 -14 -01 7 HRS. EQUIPMENT AND 2 MEN 212.00 2 L.S. TELEVISION SURVEYS (NO CHARGE ON 2 1,375.00 OTHERS) Subtotal ADDITIONAL HELPER FOR INSTALLATION OF 2" FLUSH -JOINT PVC AND TRANSDUCER 22.50 HRS. ADDITIONAL HELPER 72.00 Subtotal 705.50 2,920.00 1,219.50 2,920.00 2,058.00 498.00 1,484.00 2,750.00 14,555.00 1,620.00 1,620.00 Layne Christensen Company will institute a late payment charge at a rate of 18% per annum (unless a lower rate is required under applicable law, in which case the lower rate shall apply) for all payments not made on or before the due date. It is the policy of Layne Christensen to preserve all lien and payment bond rights where available. All notifications are sent strictly for this purpose. - 000RI- Thank you for your business Remittance Copy Layne Christensen is an Equal Opportunity Employer (Continued) Layne Christensen Company LAYNE- WESTERN DIVISION Remit to: P.O. Box 91090 Chicago, IL 60693 721 West Illinois Avenue - Aurora, Illinois - 60506 -2892 Phone (630) 897 -6941 Fax (630) 897 -6976 229 West Indiana Avenue - Beecher, Illinois - 60401 -0489 Phone (708) 946 -2244 Fax (708) 946 -9415 INVOICE 10162896 SOLD TO: VILLAGE OF LEMONT 418 MAIN STREET LEMONT, IL 60439 TERMS: Due on receipt Page: 3 of 3 DATE: 06/18/2001 PO # CONTRACT OUR ORDER NO.: 168650 CLIENT NO.: 10160047 QUANTITY DESCRIPTION AMOUNT TOTAL - ADDITIONAL MATERIALS - 1 L.S. 2" PVC FLUSH -JOINT PIPE FOR TRANSDUCER 83 FT. 10" SCHEDULE 40 PRIME STEEL LINER PIPE 1 L.S. 10" LINER SHOE 1,425.00 37.50 775.00 Subtotal ADDITIONAL MATERIALS 1 L.S. LESS PREVIOUSLY COMPLETED WORK (INCL. (92,245.75) RETAINAGE AMOUNT) Subtotal - RETAINAGE - 1 L.S. -ADD FOR PREVIOUS RETAINAGE 9,224.58 Subtotal RETAINAGE 1,425.00 3,112.50 775.00 5,312.50 (92,245.75) (92,245.75) 9,224.58 9,224.58 Total Amount Total Tax 83,322.33 0.00 Total Invoice 83,322.33 Layne Christensen Company will institute a late payment charge at a rate of 18% per annum (unless a lower rate is required under applicable law, in which case the lower rate shall apply) for all payments not made on or before the due date. It is the policy of Layne Christensen to preserve all lien and payment bond rights where available. All notifications are sent strictly for this purpose. - 000RI- Thank you for your business Remittance Copy Layne Christensen is an Equal Opportunity Employer