R-53-03 Authorizing Approval Of An engineering Agreement With Strand Associates, Inc. For Design And Construction Services For Well #6RESOLUTION 11\, 3 -03
RESOLUTION AUTHORIZING APPROVAL OF AN ENGINEERING
AGREEMENT WITH STRAND ASSOCIATES, INC.
FOR DESIGN AND CONSTRUCTION SERVICES FOR WELL #6
WHEREAS, the Village of Lemont requires engineering services related to design and
construction services for a new well and softening plant to meet future needs of the community; and
WHEREAS, the Village seeks to utilize the firm of Strand Associates, Inc. to design and
prepare specifications for Well #6; and
WHEREAS, the Village and Strand Associates, Inc. have negotiated an agreement to
identify the terms and conditions of the services to be provided.
NOW, THEREFORE, BE IT RESOLVED, by the President and Board of Trustees that
the Engineering Fee Proposal attached hereto as Exhibit A is hereby approved.
PASSED AND APPROVED BY THE PRESIDENT AND BOARD OF TRUSTEES OF
THE VILLAGE OF LEMONT, COUNTIES OF COOK, WILL AND DU PAGE, ILLINOIS,
on this 28th day of July , 2003.
AYES NAYS PASSED ABSENT
Debby Blatzer V
Peter Coules V
Brian Reaves
Steven Rosendahl ✓
Ronald Stapleton
Jeanette Virgilio ✓
Attest:
JO F. P AZZA, Village
4'I2Ut/k
lUi)/14614(
SMOLLEN, Village Clerk
Sa
STRAND
ASSOCIATES, INC..
E N G I N E E R S
910 West Wingra Drive
Madison, WI 53715
Phone: 608-251-4843
Fax: 608-251-8655
Strand Associates, Inc.
Madison, WI
Joliet, IL
Louisville, KY
Subsidiary Offices
PEH
Lexington, KY
Louisville, KY
Division Offices
SIECO
Columbus, IN
Lancaster, OH
TAI
Mobile, AL
www.strand.com
July 3, 2003
Mr. Dan Fielding, Director of Public Works
Village of Lemont
418 Main Street
Lemont, IL 60439
Re: Engineering Fee Proposal for Well No. 6 Facilities with Softening Plant
Dear Mr. Fielding:
At your request, we have prepared an engineering fee proposal for the design of a new
deep well facility for the Village of Lemont. The facility will be housed in a masonry
building and will include a new 1,650- foot -deep well, well pumping equipment, and ion
exchange treatment to reduce anticipated elevated radium levels. This proposal also
includes construction- related services for the deep well only.
Engineering Services
Design services envisioned for the Well No. 6 will include preliminary planning,
topographic surveys, final design, plan and specification preparation, and IEPA
submittals. Specific components are noted below:
1. A new deep well, which will be drilled to a depth of approximately 1,650 feet
and cased to a depth of 1,050 feet to case off the upper St. Peter sandstone.
2. Pumping facilities, which will be housed in a masonry building designed to
reflect the architectural appearance of nearby condominiums. Facilities will
include a submersible well pump, chemical room, electrical gear, and controls
tied into the existing SCADA system.
3. An ion exchange plant consisting of an automatic zeolite softener, sized to treat
75 percent of total well flow.
Construction services for the deep well will include bidding assistance (including
duplication), shop drawing review, general observation, contract administration, and
part-time, on -site construction observation.
Engineering Fees
The proposed engineering services shall be provided on an hourly fee basis for the time
actually spent on the project (plus expenses) per our standard billing procedure.
Sa
STRAND
ASSOCIATES, INC..
E N G I N E E R S
Mr. Dan Fielding, Director of Public Works
Village of Lemont
Page 2
July 3, 2003
Proposed engineering fees do not include legal surveys, IEPA loan applications, soil
borings, design of a major ground -level reservoir, construction services for the well
house and treatment facility, or any specialized investigations including archeological,
hazardous waste, or flood evaluations.
The total estimated engineering fee for the Well No. 6 facility design with well borehole
construction services is $129,500, with the following anticipated breakdown.
Item Description Amount
Design (through bidding)
Deep Well $ 15,000
Well Facility 63,000
Treatment 41,500
Subtotal $119,500
Construction Services
Deep Well 10,000
Engineering Budget $129,500
If this proposal is acceptable to the Village, please let us know and we will begin work
on the project immediately. If you have any questions or would like additional
information, please call.
Sincerely,
STRAND ASSOCIATES, INC.
Gerald D. Groth, P.E.
ACCEPTED:
Attest:
GDG:mro \G: \SDATA \ @Sai \401 -- 450 \424 \010 \Wrd \Well 8 proposal.doc
Village of Faith
Mayor
John F. Piazza
Village Clerk
Charlene M. Smollen
Trustees
Debby Blatzer
Peter Coules
Brian Reaves
Steven Rosendahl
Ronald Stapleton
Jeanette Virgilio
Administrator
Gary C. Holmes
Village of Lemont
August 6, 2003
Gerald D. Groth, P.E.
Strand Associates, Inc.
910 West Wingra Drive
Madison, WI 53715
418 Main Street • Lemont, Illinois 60439
Administration RE: Engineering Fee Proposal for Well No. 6 Facilities with Softening Plant
phone (630) 257 -1590
fax (630) 243 -0958
Building Department
phone (630) 257 -1580
fax (630) 257 -1598
Community Development
phone (630) 257 -1595
fax (630)257 -1598
Dear Gerry:
Enclosed is a copy of Resolution R -53 -03 approving the attached Engineering Fee
Proposal from Strand Associates for design and construction services related to Well
#6, approved by the Village Board on July 28, 2003.
Economic Development If any additional information is needed at this time, don't hesitate to call me at 630 -
phone (630) 257 -6440 257 -2532.
fax (630) 243 -0958
Engineering Department Sincerely,
phone (630) 243 -2705
fax (630) 257 -1598 %�
Finance Department F' -i
phone (630) 257 -1550
fax (630) 257 -1598 Dan Fielding
Director of Public Works