R-38-08 06/09/2008RESOLUTION R.-?j g D RESOLUTION AUTHORIZING APPROVAL OF CHANGE ORDER #4 TO THE GMAX POLICE BUILDING CONTRACT WITH WIGHT FOR CONSTRUCTION OF A SHARED PARKING LOT WHEREAS, the Village of Lemont approved a design/build contract with Wight Construction for the construction of its new Police Facility; and WHEREAS, the contract with Wight Construction included a Guaranteed Maximum Price for the scope of the contract; and WHEREAS, the Village of Lemont requires an increase in scope to include the construction of a shared parking lot on the St. Matthews property; and WHEREAS, the construction of the shared parking lot was not included in the scope of the original Guaranteed Maximum Price Contract but will be added as a change order to said contract; NOW, THEREFORE, BE IT RESOLVED by the President and Board of Trustees that a Change Order to the Guaranteed Maximum Price Contract with Wight Construction shall be authorized for $56,169.15. PASSED AND APPROVED BY THE PRESIDENT AND BOARD OF TRUSTEES OF THE VILLAGE OF LEMONT, COOK, WILL AND DU PAGE COUNTIES ILLINOIS on this 44-k Day of , 2008 Debby Blatzer Peter Coules Brian Reaves Cliff Miklos Ronald Stapleton Jeanette Virgilio Attest: AYES V v ✓ NAYS PASSED ABSENT JOHN F. ' i AZZA, Village Pr ENE SMOLLEN, Village Clerk DESIGN BUILDER CHANGE ORDER VILLAGE OF LEMONT POLICE FACILITY Village of Lemont 418 Main Street Lemont, IL 60439 Design Builder's Project No.: 07- 5011 -03 TO: Wight Construction, Inc. 2500 N. Frontage Road Darien, IL 60581 630 -969 -7000 You are hereby directed to make the following changes in the Contract: WIGHT CONSTRUCTION, INC. 2500 N. Frontage Road Darien, IL 60561 Design Build / Construction Management DATE: 5/5/2008 Prepared By. Approved By CHANGE ORDER NUMBER: VOL-04 CONTRACT FOR: 004 -002 - Design Build Services CONTRACT DATE: 3/3/2008 Item - Description Quantity Unit Price Net Amount 01 Increase scope to Include the construction of the shared parking lot on the St. Matthew property and associated Design/CM Services Grading 6 Excavation $ 6,900.00 Concrete $ 9,500.00 Asphalt $32,828.00 Sub Total Hard Cost 549,228.00 CM Fee 3.5% NE Fee 7.6% Contingency 3.0% $ 1,722.98 $ 3,741.33 $ 1,476.84 Total 556,169.15 1.000 $56,169.15 $56,189.15 Total: $56,169.15 Not valid until signed by the Design Builder Signature of the Contractor indicates his agreement herewith, including any adjustment in the Contract Sum or contract time. The original Contract Sum was: Net change by previously authorized requests and changes: The Contract Sum prior to this Change Order was: The Contract Sum will be Increased by this Change Order: The new Contract Sum including this Change Order will be: The Contract Time will not be changed. The Date of Substantial Completion as of this Change Order therefore is $7,724,293.00 $50,219.98 $7,774,512.98 $56,169.15 $7,830,682.13 Authorized: DESIGN BUILDER: OWNER: Wight Construction, Inc. Village of Lemont 2500 N. Frontage Road 418 Main et Darien. IL 60561 Lemont ,, NIIIIMIN By: Date: f co_01 vight_dbco By: Date: