R-39-08 06/09/2008RESOLUTION • 39 , os
RESOLUTION AUTHORIZING APPROVAL OF A CHANGE ORDER #6
TO THE GMAX POLICE BUILDING CONTRACT WITH WIGHT FOR
LOW VOLTAGE SERVICES: VOICE/DATA CABLING & EQUIPMENT
WHEREAS, the Village of Lemont approved a design/build contract with Wight Construction for the
construction of its new Police Facility; and
WHEREAS, the contract with Wight Construction included a Guaranteed Maximum Price for the
scope of the contract; and
WHEREAS, the Village of Lemont requires low voltage services: Voice/Data Cabling & Equipment
in conjunction with the Lemont Police Facility construction contract; and
WHEREAS, these low voltage services were not included in the scope of the original Guaranteed
Maximum Price Contract but will be added as a change order to said contract;
NOW, THEREFORE, BE IT RESOLVED by the President and Board of Trustees that a Change
Order to the Guaranteed Maximum Price Contract with Wight Construction shall be authorized for $61,921.23.
PASSED AND APPROVED BY THE PRESIDENT AND BOARD OF TRUSTEES OF
THE VILLAGE OF LEMONT, COOK, WILL AND DU PAGE COUNTIES ILLINOIS on this
Day of , 2008
Debby Blatzer
Peter Coules
Brian Reaves
Cliff Miklos
Ronald Stapleton
Jeanette Virgilio
Attest:
AYES NAYS PASSED ABSENT
v
v
V"
CHARLENE SMOLLE , Village Clerk
resident
DESIGN BUILDER CHANGE ORDER
VILLAGE OF LEMONT POLICE FACILITY
Village of Lemont
418 Main Street
Lemont, IL 60439
Design Builder's Project No.: 07- 5011 -03
TO: Wight Construction, Inc.
2500 N. Frontage Road
Darien, IL 60561
630- 969 -7000
You ere hereby directed to make the following changes In the Contract:
WIGHT CONSTRUCTION, INC.
2500 N. Frontage Road
Darien, IL 60561
Design Build / Construction Management t4 /
Prepared By:
Approved By: `fib
DATE: 5/5 /2008
CHANGE ORDER NUMBER: VOL -06
CONTRACT FOR: 004 -002 - Design Build Services
CONTRACT DATE: 3/3/2008
Item Description
01 Increase scope to include technology wiring, devices and racks for phone, data, sound
reinforcement, speakers and CATV and associated CM Services.
Technology
Sub Total Hard Cost
CM Fee 3.5%
NE Fee 0.0%
Contingency 3.0%
Total
$58.142.00
$58,142.00
$ 2.034.97
$ 0.00
$ 1,744.26
$61.921.23
Quantity Unit Pride
1.000 $61,921.23
Total:
$61,921.23
$61,921.23
Not valid until signed by the Design Builder
Signature of the Contractor indicates his agreement herewith, Including any adjustment in the Contend Sum or contract time.
The original Contract Sum was:
Net change by previously authorized requests and changes:
The Contract Sum prior to this Change Order was:
The Contract Sum will be Increased by this Change Order:
The new Contract Sum including this Change Order will be:
The Contract Time will not be changed.
The Date of Substantial Completion as of this Change Order therefore is
$7,724,293.00
$107,972.14
$7,832,265.14
$61,921.23
$7,894,186.37
Authorized:
DESIGN BUILDER:
Wight Construction, Inc.
2500 N. Frontage Road
Darien, IL 60561
By:
Date:
f_co_O1 wight_dbco
OWNER:
Village of Lemont
418 Main Street
Lemont, IL 60439
By:
Date: