Loading...
R-87-26 Approving Professional Services Agreement Between HR Green, Inc. and the Village of Lemont, Illinois for Crossing Creek Archer Avenue Sidewalk Design EngineeringVILLAGE k_M�2_)o VILLAGE Or 418 Main Street I Lemont, IL 60439 TO: Village Board Meeting FROM: Ted Friedley, Public Works THROUGH: SUBJECT: A Resolution Approving Professional Services Agreement Between HR Green, Inc. and the Village of Lemont, Illinois for Crossing Creek Archer Avenue Sidewalk Design Engineering DATE: October 13, 2026 SUMMARY/BACKGROUND HR Green is assisting the Village with design engineering services for the Archer Avenue sidewalk that was never installed as part of the Crossing Creek Subdivision over 20 years ago. Archer Avenue is and IDOT roadway, so an IDOT permit will be necessary to install the new sidewalk. The IDOT review process will require a full set of plans and specifications. Due to the time span since the subdivision plans, IDOT will not accept those plans as part of their permitting process now. The total time and material, not to exceed, fees for the project are $53,000.00. ANALYSIS The Crossing Creek / Archer Avenue Sidewalk project is needed to fix a wrong from over 20 years ago. THe residents of Crossing Creek contact Village Staff regularly about their concerns with not being able to leave their cul-de-sac by any other means other than vehicular because the sidewalk was never installed per plan. Consistency with Village Policy STAFF RECOMMENDATION Pass A Resolution Approving Professional Services Agreement Between HR Green, Inc. and the Village of Lemont, Illinois for Crossing Creek Archer Avenue Sidewalk Design Engineering BOARD ACTION REQUESTED Pass A Resolution Approving Professional Services Agreement Between HR Green, Inc. and the Village of Lemont, Illinois for Crossing Creek Archer Avenue Sidewalk Design Engineering ATTACHMENTS A Resolution Approving Professional Services Agreement Between HR Green, Inc. and the Village of Lemont, Illinois for Crossing Creek Archer Avenue Sidewalk Design Engineering.pdf VILLAGE OF LEMONT RESOLUTJON NUMBER R- q-26 A RESOLUTION APPROVING PROFESSIONAL SERIVCES AGREEMENT BETWEEN HR GREEN, INC. AND THE VILLAGE OF LEMONT, ILLINOIS FOR CROSSING CREEK ARCHER AVENUE SIDEWALK DESIGN ENGINEERING JOHN EGOFSKE, Village President CHARLENE M. SMOLLEN, Clerk SAMUEL J. FORZLEY JANELLE KITTRIDGE KEN MCCLAFFERTY KEVIN SHA UGHNESSY RICK SNIEGOWSKI RON STAPLETON Trustees Published in pamphlet form by authority of the Village President and Board of Trustees of the Village of Lemont od q-J026 RESOLUTION NO. R-q 26 A RESOLUTION APPROVING PROFESSIONAL SERIVCES AGREEMENT BETWEEN HR GREEN, INC. AND THE VILLAGE OF LEMONT, ILLINOIS FOR CROSSING CREEK ARCHER AVENUE SIDEWALK DESIGN ENGINEERING WHEREAS the Village of Lemont, Counties of Cook, Will, and DuPage, Illinois, ("the Village") is a municipality in the State of Illinois with full powers to enact Ordinances and adopt Resolutions for the benefits of the residents of the Village; and WHEREAS, the Village and HR Green, Inc. wish to enter a professional services agreement for Crossing Creek Archer Avenue Sidewalk Design Engineering as further outlined in the professional services agreement attached hereto as Exhibit A ("Agreement"); and WHEREAS, the Mayor and Board of Trustees find that it is in the best interests of the Village to authorize the Agreement attached hereto as Exhibit A. NOW, THEREFORE, BE IT RESOLVED by the President and Board of Trustees of the Village of Lemont, Counties of Cook, Will and DuPage, Illinois, as follows: SECTION 1: That the above recitals and legislative findings are found to be true and correct and are hereby incorporated herein and made a part hereof as if fully set forth in their entirety. SECTION 2: The Mayor and Board of Trustees of the Village of Lemont hereby approve the Agreement with HR Green, Inc. in substantially the same form as attached hereto as Exhibit A, subject to attorney review. SECTION 3: The Mayor and Clerk are hereby authorized, respectively, to execute the Agreement with HR Green, Inc. S ..C..TION 4! This Resolution, and its parts, are declared to be severable and any section, subsection, sentence, clause, provision, or portion of this Resolution that is declared invalid such decision shall not affect the validity of any other portion of this Resolution, which shall remain in full force and effect. SECTION 5: All Resolutions and Ordinances in conflict herewith are hereby repealed to the extent of such conflict. PASSED AND APPROVED BY THE PRESIDENT AND BOARD OF TRUSTEES OF THE VILLAGE OF LEMONT, CO ri OF COOK, WILL, AND DUPAGE, ILLINOIS, ON THIS I ? DAY OF 0& 6V 2026. Samuel J. Forzley Janelle Kittridge Ken McClafferty Kevin Shaughnessy Rick Sniegowski Ron Stapleton ATTEST: PRESIDENT AND VILLAGE BOARD MEMBERS: AYES: NAYES V V W—U "—, 41k, CHARLENE M. SMOLLE 4 V' ge Clerk � pF Q ABSENT: ABSTAIN: - - ��o JOHN EGOFSKE President �2 v � . S IVA /L Ll Ncbo Exhibit A Crossing Creek Archer Avenue Sidewalk Design Engineering Agreement HRGreen. PROFESSIONAL SERVICES AGREEMENT For Lemont, IL — Crossing Creek Sidewalk — Design Engineering Prepared For: Village of Lemont Mr. George Schafer Village Administrator 418 Main Street Lemont, IL 60439 Ph: 630.257.1550 Prepared By: Bruce A. Hill, PE Municipal Executive — Municipal Services Engineering HR Green, Inc. 323 Alana Drive New Lenox, IL 60451 815.462.9324 Project No. 2602968 October 8, 2026 Version 2.3 02052021 TABLE OF CONTENTS 1.0 PROJECT UNDERSTANDING 2.0 SCOPE OF SERVICES 3.0 DELIVERABLES AND SCHEDULES INCLUDED IN THIS AGREEMENT 4.0 ITEMS NOT INCLUDED IN AGREEMENT/SUPPLEMENTAL SERVICES 5.0 SERVICES BY OTHERS 6.0 CLIENT RESPONSIBILITIES 7.0 PROFESSIONAL SERVICES FEE 8.0 TERMS AND CONDITIONS Version2.3 02052021 HRGreen. Professional Services Agreement Lemont, IL — Crossing Creek Sidewalk-IDOT HR Green Project No.: 2602968 October 8, 2026 Page 1 of 9 THIS AGREEMENT is between the Village of Lemont (hereafter "CLIENT") and HR Green, Inc. (hereafter "COMPANY"). 1.0 Project Understanding 1.1 General Understanding CLIENT is proposing to make pedestrian improvements along the northwest side of Archer Ave. (IDOT Rte. 171) to close the existing gap between Ashford Drive and 1271h Street. The proposed sidewalk was to be included as part of the Crossing Creek development decades ago but was never completed. CLIENT wishes to proceed with permitting and final engineering design for these improvements. COMPANY will complete the preliminary and final engineering, which will generally include topographic survey, sidewalk design, environmental review, initial drainage review, plats and legals, contract plans, bidding services, Illinois Department of Transportation (IDOT) permitting and other specific tasks as described in this AGREEMENT. The final engineering including the Phase II contract plans, contract documents, IDOT permitting, other relevant agency coordination, and bidding services will be completed under a separate, future agreement. This project's major scope items will include the installation of a five (5) foot wide sidewalk along the northwest side of Archer Avenue. The improvements will begin northeast of Ashford Drive and extend northeast approximately 800 feet to connect into an existing sidewalk located at the Lemont Township Highway Department. Since Archer Avenue (Rte. 171) is under the jurisdiction of IDOT, review and approval of the improvements will be required from the local IDOT district. In addition, the Illinois State Toll Highway Authority (Tollway) has ownership of a narrow strip of right-of-way (ROW) south of Hansen Court and depending on the location/alignment of the sidewalk, Tollway review and approval may also be necessary/required. Preparation of ROW documents are included in this AGREEMENT by COMPANY. The ROW acquisitions (including appraisals and negotiations) will be completed by CLIENT. During the preliminary engineering development, all ROW needs will be determined. 1.2 Design Criteria/Assumptions The engineering and contract documents will be developed according to the applicable requirements within the following design guidelines: a) Bureau of Local Roads and Streets (BLR) Manual b) Public Right -of -Way Accessibility Guidelines (PROWAG) c) Village ordinances (as applicable) Version2.3 02052021 ® Professional Services Agreement Lemont, IL —Crossing Creek Sidewalk-IDOT HR Green Project No.: 2602968 October HRGreen ® Page 2 of 9 2.0 Scope of Services The CLIENT agrees to employ COMPANY to perform the following services 2.1 Land Survey Services A. Right -of -Way Survey COMPANY will recover existing ROW evidence for approximately 850 feet (0.16 miles) along the northwest side of Archer Ave from the center line of Crossing Creek Dr extending 320 feet southwest toward Ashford Dr and 530 feet northeast toward the Lemont Township Highway Department building at 12750 Archer Ave. COMPANY will calculate the existing ROW as shown on the existing ROW documents (provided by CLIENT or secured from IDOT) and/or adjacent recorded plats of subdivision to include on the base map. B. Topographic Survey COMPANY will complete a topographic survey, which will include the area lying within the existing ROW for the limits described above. Roadway cross -sections will be surveyed at 50-foot intervals and extend from the northerly edge of pavement to 10 feet beyond the northerly ROW line. The survey will include existing visible features and improvements. Existing utilities will be surveyed from visible flags or markings. Storm sewer, sanitary sewer, and water main structures will be surveyed, including rim and invert elevations, pipe sizes, and direction as observed at unlocked manholes. Trees lying within the limits described above and having a diameter of six (6) inches or greater will be located and referenced within the base map. The tree survey will NOT include species identification, health, or structure information. The survey will reference existing NGS control stations, Illinois State Plane Coordinate System East Zone NAD83 (2011) and NAVD88 (US Survey Feet). C. Base Map COMPANY will generate an AutoCAD Civil 3D 2026 drawing/base map, and terrain model including one (1) foot contour intervals, of the existing features collected within the project limits according to IDOT standards. The topographic survey base map will show tags to existing visible utilities and features, where appropriate. A topographic survey plat will NOT be provided. 2.2 Preliminary Engineering A. Data Collection and Review COMPANY will request from CLIENT any available documents, studies, and files developed for the project corridor. B. Preliminary Design Studies Preliminary sidewalk geometrics for the northwest side of Archer Ave. will be developed by COMPANY. COMPANY will coordinate with CLIENT to develop the proposed alignment within the project limits. The following tasks will be completed by COMPANY: Version2.3 02052021 HRGreen® Professional Services Agreement Lemont, IL — Crossing Creek Sidewalk-IDOT HR Green Project No.: 2602968 October 8, 2026 Page 3 of 9 1. COMPANY will develop sidewalk geometrics for Archer Ave from northeast of Ashford Drive to southwest of 1271h Street, a length of approximately 800 feet. 2. COMPANY will prepare a proposed typical section for sidewalk along Archer Ave. 3. COMPANY will review existing topography and proposed grading for determination of ROW acquisition needs. ROW acquisition is not anticipated but could be required depending on grading challenges or utility conflicts. 4. COMPANY will prepare two (2) plan and profile (P&P) sheets (one (1) inch = 20 feet) including necessary preliminary engineering level detail of the proposed new sidewalk design. The sheets will be double -paned, detailing the proposed sidewalk improvements in the two (2) views (top panel = plan view and the bottom panel = profile view). 5. COMPANY will prepare an exhibit showing the horizontal layout of the proposed improvements on an aerial base map at a scale of one (1) inch = 100 feet. 6. COMPANY will design two (2) proposed ADA ramp crossings at Crossing Creek Drive, which will be designed to comply with IDOT and PROWAG standards. 7. COMPANY will provide construction details sheets for erosion control, traffic control and protection, landscape restoration, and maintenance of traffic. 8. COMPANY will prepare a Preliminary Engineer's Opinion of Probable Construction Cost (EOPC) for CLIENT's use. C. Drainage Investigation COMPANY will calculate the change in impervious area due to the addition of the sidewalk. It is anticipated that the proposed sidewalk installation will not require any drainage investigation as the increased impervious area will be below permitting threshold. There are no floodplains or known existing drainage problems within the project limits. If it is determined that additional drainage investigation is necessary, it will be included in the final engineering agreement. D. Utility Coordination The Archer Avenue corridor within the project limits has a number of franchise utilities including electric, gas, cable, and telephone. The proposed sidewalk design will minimize impacts to the existing utilities to the extent practical. It will be necessary that utilities are identified and located to assist in developing a sidewalk alignment to avoid/minimize utility conflicts during construction. The utility coordination tasks will include the following: 1. COMPANY will coordinate with utility companies found to have facilities located within the vicinity of the project limits. An initial J.U.L.I.E. design ticket will be submitted to determine those that have facilities within the project limits. Requests will be made to utilities to provide information on their service lines. Version2.3 02052021 HRGreen® Professional Services Agreement Lemont, IL — Crossing Creek Sidewalk-IDOT HR Green Project No.: 2602968 October 8, 2026 Page 4 of 9 2. Utility information received will be added to project's CADD files for use in design to determine if/what utilities will be impacted based on the proposed improvements to be provided within the project limits. 3. COMPANY will prepare and distribute project plans to affected utility owners and request reviews to identify actual or potential conflicts with the proposed sidewalk. 4. COMPANY will conduct and document utility coordination meetings and correspondence with utility owners and CLIENT throughout the design phase. Utility relocation information to be incorporated into the project plans, specifications, and schedule as appropriate. E. Environmental Studies CLIENT has indicated that this section of right-of-way and adjacent parcels do not hold any historic value, is not listed as historic property or landmark, and obtaining ROW for grading purposes will be possible. The following is a summary of the environmental resources and anticipated involvement for this project: 1. Wetlands — Based upon the latest Cook County mapping, no wetlands are located within the project corridor. No delineation is included. 2. Special Waste — Due to the limited excavation anticipated on this project and it is recommended that the project be risked managed to eliminate the cost for special waste testing. It is anticipated that the excavated material soil will remain on site; however, if needed, excess material can be removed to a CCDD site. Discussions with CLIENT will be held on how best to handle excavated material prior to beginning the final design. 3. Cultural - No impacts anticipated. COMPANY will submit review request to Illinois Historical Society. 4. Natural Resources — No impacts are anticipated at this time; however, COMPANY will review if tree replacement will be feasible. The type, structure, and/or health of the impacted trees will not be collected. 5. Biological/Threatened and Endangered (T&E) Species — An EcoCAT submittal will be made to Illinois Department of Natural Resources (IDNR) by COMPANY to verify there are no impacts to any T&E species. 6. Floodplains - No impacts anticipated. There are no floodplains within the corridor. F. IDOT Permitting 1. COMPANY will prepare submittal package for the IDOT District Permit Office which will include cover letter, location maps, preliminary sidewalk design, and all other information that may be required for IDOT's review and approval of the project. IDOT District Permit Office will provide review letter comments to be addressed on the final engineering plan. Version2.3 02052021 HRGreen® Professional Services Agreement Lemont, IL — Crossing Creek Sidewalk-IDOT HR Green Project No.: 2602968 October 8, 2026 Page 5 of 9 2. Submittal is also anticipated to be reviewed by IDOT's ADA coordinator, which may generate additional comments for Crossing Creek Drive crossing ramps. 3. COMPANY will coordinate with IDOT and revise plans and provide additional studies as needed to receive approval for construction of the sidewalk. 2.3 Final Engineering A. Final Design Phase Services will include construction plans as described in the Preliminary Design Phase with all additional sheets and revisions as needed to obtain IDOT permit approval. B. Construction drawings are anticipated to include the following sheets: General 1. Cover Sheet with Location Map and Sheet Index 2. General Construction Notes, Standard Symbols, Summary of Quantities ('.ivil Planc 3. Existing Conditions 4. Sidewalk southwest of Crossing Creek Drive P&P Sheet (1"=20') 5. Sidewalk northeast of Crossing Creek Drive P&P Sheet (1"=20') 6. ADA Crossing Details at Crossing Creek Drive 7. Erosion Control Plan Construction Details 8. IDOT ADA Sidewalk Details 9. Illinois DOT Highway Standard Details (Traffic Control & Protection) 10. Erosion & Sediment Control Details and Specifications C. Provide an internal quality assurance and quality control review of final documents. D. Submit three (3) copies of the drawings, specifications, contract documents, and Opinion of Probable Cost at the 90% complete milestone to CLIENT for review. E. Develop a final project schedule for advertisement, bidding, and construction completion. F. Assist with bid opening and bid tab for awarding project. 2.4 Meetings and Coordination COMPANY will attend the following meetings and field checks: A. CLIENT Meetings — Two (2) COMPANY representatives will attend up to two (2) status/coordination meetings to discuss the project. These meetings will take place virtually. B. Agency and Stakeholder Meetings — Status/coordination meetings will be held to discuss the project. These meetings may take place at CLIENT's office, project site or virtually. Version2.3 02052021 HRGreen. Professional Services Agreement Lemont, IL — Crossing Creek Sidewalk-IDOT HR Green Project No.: 2602968 October 8, 2026 Page 6 of 9 C. Project Coordination and Correspondence - COMPANY will conduct general coordination throughout the project with CLIENT, IDOT, businesses, residents, Tollway, various other stakeholders, and any utility companies having facilities within project limits. This item includes, but is not limited to letters, telephone and e-mail correspondence, and the filing of information. 2.5 Administration & Management COMPANY will conduct general project administration throughout the duration of the project, including management and oversight of the project schedule; periodic review of the project execution; document control; scope, schedule, and budget monitoring; billing and invoicing; and contract file management. 3.0 Deliverables and Schedules Included in this Agreement 1. Notice to Proceed — NTP......................................................................... October 15, 2026 2. Preliminary Engineering For Village Review ......................................December 9, 2026 3. Submit Document for Permitting .................................................. December 9, 2026 4. Final Documents....................................................................................... May 21, 2027 5. CLIENT Bid opening....................................................................................... June 14, 2027 6. CLIENT Council award contract..................................................................... July 8, 2027 7. Contractor Start (Anticipated — T.B.D.)..............................................................July 26, 2027 8. Project Completion Date...............................................................................September 2027 This schedule was prepared to include reasonable allowances for review and approval times required by the CLIENT and public authorities having jurisdiction over the project. This schedule shall be equitably adjusted as the project progresses, allowing for changes in the scope of the project requested by the CLIENT or for delays or other causes beyond the control of COMPANY. 4.0 Items not included in Agreement/Supplemental Services The following items are not included as part of this AGREEMENT: • Tree Identification, Health, or Structure Survey • Topographic Survey Plat • ROW Acquisition Services • Drainage Investigations • Project Development Report • Studies and/or coordination related to Social/Economic, Agricultural, Air Quality, or Special Lands resources/impacts • Noise Study • Biological/T&E species impacts/mitigation • Specialty landscaping • Construction Observation/Construction Layout Supplemental services not included in the AGREEMENT can be provided by COMPANY under separate agreement, if desired. Version2.3 02052021 HRGreen® 5.0 Services by Others 1. Seeco Consultants, Inc. Professional Services Agreement Lemont, IL — Crossing Creek Sidewalk -]DOT HR Green Project No.: 2602968 October 8, 2026 Page 7 of 9 COMPANY has included a budgetary amount for geotechnical sub -consultant to provide all professional services necessary to evaluate excavated soil for disposal at an IEPA permitted Clean Construction or Demolition Debris (CCDD) facility and/or Uncontaminated Soil Fill Operation (USFO) as required. This work will include but is not limited to sample collection, laboratory testing, preparation and execution of LPC-662 and/or LPC-663 as required by the receiving CCDD or USFO facility. 6.0 Client Responsibilities 1. Provide site development concept plan showing sidewalk to north and south that COMPANY is tying into and any other pertinent information. 2. Provide City Utility Atlases and GIS information as needed. 3. Review documents, reports, exhibits, letters, etc. in a timely manner so as not to negatively impact the project schedule. 7.0 Professional Services Fee 7.1 Fees The fee for services will be based on COMPANY standard hourly rates current at the time the AGREEMENT is signed. These standard hourly rates are subject to change upon 30 days' written notice. Non -salary expenses directly attributable to the project such as: (1) living and traveling expenses of employees when away from the home office on business connected with the project; (2) identifiable communication expenses; (3) identifiable reproduction costs applicable to the work; and (4) outside services will be charged in accordance with the rates current at the time the service is done. 7.2 Invoices Invoices for COMPANY's services will be submitted, on a monthly basis. Invoices will be due and payable upon receipt in accordance with the Illinois Prompt Payment Act 50ILCS 505. If any invoice is not paid within these timelines, COMPANY may, without waiving any claim or right against the CLIENT, and without liability whatsoever to the CLIENT, suspend or terminate the performance of services. 7.3 Extra Services Any service required but not included as part of this AGREEMENT shall be considered extra services. Extra services will be billed on a Time and Material basis with prior approval of the CLIENT. 7.4 Exclusion This fee does not include attendance at any meetings or public hearings other than those specifically listed in the Scope of Services. These service items are considered extra and are billed separately on an hourly basis. Version2.3 02052021 HRGreen® Professional Services Agreement Lemont, IL — Crossing Creek Sidewalk-IDOT HR Green Project No.: 2602968 October 8, 2026 Page 8 of 9 7.5 Payment The CLIENT AGREES to pay COMPANY on the following basis: Time & Material, not to exceed the amount of $53,000.00. The breakdown of fee is as follows: Task Fee (T&M basis) Project Management, Meetings, Administrative Services $ 3,500.00 Site Survey & Data Collection $ 11,500.00 Geotechnical Sub -Consultant $5,000.00 Design Phase Services (Preliminary) $ 14,500.00 Permitting Through Jurisdictional Agencies $ 6,000.00 Design Phase Services (Final) $ 8,500.00 Bid Phase Services $ 4,000.00 Total $53,000.00 8.0 Terms and Conditions This Agreement is an addendum to and is considered part of the Master Agreement between CLIENT and COMPANY. All terms and conditions contained in that agreement apply to this Agreement. Version2.3 02052021 HRGreen® Professional Services Agreement Lemont, IL — Crossing Creek Sidewalk-IDOT HR Green Project No.: 2602968 October 8, 2026 Page 9 of 9 This AGREEMENT is approved and accepted by the CLIENT and COMPANY upon both parties signing and dating the AGREEMENT. Services will not begin until COMPANY receives a signed agreement. COMPANY's services shall be limited to those expressly set forth in this AGREEMENT and COMPANY shall have no other obligations or responsibilities for the Project except as agreed to in writing. The effective date of the AGREEMENT shall be the last date entered below. Sincerely, HR GREEN, INC. Z 4 Bruce A. Hill Municipal Executive — Municipal Services — Engineering Approved by: ". Printed/Typed Name: Timothy J. Hartnett Title: President — Municipal Services Date VILLAGE OF LEMONT Accepted by: Printed/Typed Name Schafer October 8, 2026 Title: Village Administrator Date: J:\2026\2602968\Admin\Contract\Client\PSA_2602968_Lemont_ IL -Crossing Creek Sidewalk-IDOT Permit 2026 1008.docx Version2.3 02052021