R-14-24 Approving Award of Contract Stephen Street Structural Wall Repair Project418 Main Street Lemont, IL 60439
R Village Board Meeting
FROM: Ted Friedley, Public Works
THROUGH:
SUBJECT: A Resolution Approving Award of Contract Stephen Street Structural Wall
Repair Project
DATE: February 26, 2024
SUMMARY/BACKGROUND
Five (5) bids were received on February 2, 2024, for the Stephen Street Structural Wall Repair
project which work includes earth excavation and backfill, the removal and installation of
concrete structural wall brick veneer installation and all appurtenant construction.
The low bid amount was submitted b E.P. Wheaton, IL 60187, in the amount of $858,060.50. After discus
Y Doyel &Son, LLC, 1100 Wheaton Oaks Court,
District and E.P. Doyle & Son, LLC the best pathway for pedestrians
be determined. Some of the proposed sidewalk, and all lions with the Lemont Park
project will be removed at a cost savings of nearly $15 0 cans e that corridor h still to
Opportunities for cost savings with E.P. Doyle of the proposed striping for the
Contractor for the nearby Athens Parkproject.&Son LLC a�Oth y aee alsore lthelGeso be additional
General
ANALYSIS
Consistency with Village Policy
5-Year Capital Improvement Plan (if applicable)
STAFF RECOMMENDATION
Pass Resolution Accepting the Low Bid for Stephen Street St
the Contract Structural Wall Repair and Award
BOARD ACTION REQUESTED
Pass Resolution Accepting the Low Bid for Stephen Street St
the Contract Structural Wall Repair and Award
ATTACHMENTS
A Resolution Approving Award of Contract Stephen Street Struct
ural Wall Repair Project.pdf
VILLAGE OF LEMONT
RESOLUTION
NUMBER R-1 -24
A RESOLUTION APPROVING AWARD OF CONTRACT
STEPHEN STREET STRUCTURAL WALL REPAIR PROJECT
JOHN EGOFSKE, Village President
CHARLENE M. SMOLLEN, Clerk
JANELLE KITTRIDGE
DA VE MAHER
KEN MCCLAFFERTY
KEVIN SHA UGHNESSY
RICKSNIEGOWSKI
RONSTAPLETON
Trustees
Published in pamphlet form by authority of the Village President and Board of Trustees of the Village of Lemont ony —
-��i024
RESOLUTION NO. R-A -2
A RESOLUTION APPROVING AWARD OF CONTRACT
STEPHEN STREET STRUCTURAL WALL REPAIR PROJECT
WHEREAS the Village of Lemont requires that the Stephen Street Structural Wall Repair
project be completed; and
WHEREAS, the Village seeks to utilize the services of E.P. Doyle & Son, LLC for such
work; and
WHEREAS, E.P. Doyle & Son, LLC, 1100 Wheaton Oaks Court, Wheaton, IL 60187
submitted a low bid for such work in the amount of $858,060.50.
NOW, THEREFORE, BE IT RESOLVED by the President and Board of Trustees of
the Village of Lemont, Counties of Cook, Will and DuPage, Illinois, as follows:
SECTION 1:
The agreement attached hereto as Exhibit A is hereby approved.
SECTION 2:
The Village Administrator is hereby authorized to execute the agreement and to make
minor changes to the document prior to execution that do not materially alter the Village's
obligations, to execute any other agreements and documentation as well as to take any other steps
necessary to carry out this resolution.
SECTION 3:
This Resolution shall be in full force and effect from and after its passage and approval as
provided by law.
PASSED AND APPROVED BY THE PRESIDENT AND BOARD OF TRUSTEES OF
THE VILLAGE OF LEMONT, COUNTIES OF COOK, WILL, AND DUPAGE, ILLINOIS,
ON THIS - 2- DAY OF r $ Ir 2024.
PRESIDENT AND VILLAGE BOARD MEMBERS:
AYES: NAYES: ABSENT:
Janelle Kittridge ABSTAIN:
Dave �—
Maher —_
Ken McClafferty --- —_
Kevin Shaughnessy ------ --
Rick Sniegowski -----
Ron Stapleton — —_
JOHN EGOFSKE
ATTEST: President
CHARLENE M. S OLLEN
Village Clerk
Exhibit A
Stephen Street Structural Wall Repair Project Contract Page
Contract for Stephen Street Structural Wall Repair
1• THIS AGREEMENT, made and concluded the Leme Admiont, acting by and through the Villa day of between the Village of
g nistrator as the party of the first part, and
E.P. Doyle &Son LLC 1100
administrators, successors or assigns, Wheaton
kn Oaks Court Wheaton IL 60187 his/their executors
2• WITNESSETH: °��'n as the party of the second part.
mentioned in the Proposal hereto attached, to or and in consideration maof the
part and according to the terms expressed in the Bond referringto payments and agreements
e and performed by the party of the first
the second part agrees with said
party of expense to do all the work, furnish all the materials ass and these presents, the party of
d
work in accordance with the Plans and S he first part at his/their own proper cost and
compliance with all of the terms of this a all labor necessary to complete the
Specifications hereinafter described, and in full
under it. agreement and the requirements of the En
3' �D, it is Engineer
also understood and agreed that the
Provisions, Proposal and Contract Bond
Novotny Engineering, hereto attached Notice to Contractors, S
Y En neering, and designated ,and the Plans as Special
documents of this Contract, anare tad as Ste hen Street Structural Wall Re air all essential
part hereto.
IN
4• e WITNESS WHEREOF, the said parties have executed above mentioned. ed these presents on the date
Part of the First Part
ATTEST
F
G F The VILLA E OF L O
NT
Char ne M. Smollen, BY
_ lerl►
zw t AL � Admi ge Schafer,
tra Village
(SEAL)
Part v of the Second Part
I N � eS Corporate (If a Corporation)
Name E.P. Do le &Son LLC.
Secretary By
(Corporate Seal) President
(If a Co -Partnership)
SEAL
SEAL
Partners doing Business under the name
of
(If an Individual)
SEAL
Exhibit B
Engineer's Letter, Bid Tabulation Listing
HRGreen.
February 20, 2024
Mr. George Schafer
Village Administrator
Village of Lemont
418 Main Street
Lemont, IL 60439
Re: Stephen Street Structural Wall Repair
HR Green Proj. No.: 2303238
Dear George:
323 Alana Drive
New Lenox, IL 60451
Main 815,462.9324 + Fax 713.965.0044
HRGREEN.00M
Attached please find the tabulation sheet for the bid opened on February 2, 2024, for the subject project,
Stephen Street Structural Wall Repair Project. HR Green, Inc. has verified that out of the five (5)
bidder's, E.P. Doyle & Son, LLC. is the apparent qualified low bidder at $858,060.50 total for the complete
project. The bids range from the noted low bid up to $1,485,865.00. Our engineer's opinion of probable
construction cost for the full project was calculated as $764,120.00.
Based on the results as summarized above and because E.P. Doyle & Son, LLC. is a qualified contractor,
we recommend them to be awarded the contract at their bid prices that currently show a total amount of
$858,060.50. After discussions with Lemont Park District and E.P. Doyle & Son, LLC, the best pathway for
pedestrians in that corridor is still to be determined. Some of the proposed sidewalk and all of the proposed
striping for this project will be removed at a cost savings of nearly $15,000.00. There could also be
additional opportunities for cost savings with E.P. Doyle & Son, LLC also being the General Contractor for
the nearby Athens Park project.
If you have any questions or need additional information, please do not hesitate to contact me at
815-320-7130.
Sincerely,
HR GREEN, INC.
Z
Bruce A. Hill, P.E.
Municipal Services Executive
Enclosure
BAH/ka
J92023'2303238'Design\BidVta020524-Letter_o!_Recommendation_2024_Stephen_St_Structural_Wall Repaicdocx